1
Manual for:
50,000 BTU/H to 250,000 BTU/H
The burner shall be used only with NATURAL GAS or LP GAS as specified on the nameplate.
Warning: If the following instructions are not followed exactly, a fire or explosion may result, causing property damage, personal injury or death.
???Do not store or use gasoline or other flammable vapors and liquids in the vicinity of this or any other appliance.
-WHAT TO DO IF YOU SMELL GAS ???
???Do not try to light any appliance.
???Do not touch any electrical appliance.
???Do not use any phone in your building.
???Immediately call your gas supplier from a neighbor???s phone.
???Follow the gas supplier???s instructions.
???If you cannot reach your gas supplier, call the fire department.
???A qualified installer, service agency or the gas supplier must perform installation and service.
???All installations must be made in accordance with all state and local codes, which may differ
from instructions in this manual.
???The installer should inform and demonstrate to the user the correct operation and maintenance of the appliance.
???The installer shall also inform the user of hazards of flammable liquids and vapors and shall remove such liquids and vapors from the vicinity of the burner.
???The installation adjustment data trap, or label supplied, shall be filled in and affixed to the burner or the covered appliance.
These instructions should be affixed to the burner or adjacent to the heating appliance
NYC MEA #
Massachusetts Plumbing Board
Manufactured by Heat Wise, Inc.
1528 Rocky Point Road, Middle Island, NY 11953
rev
2
Chart 1: Natural Gas and LP
-Control System: Fenwal Model
-The system uses a remote ignition system with a separate Ignition Transformer.
-Gas Valve: VR8205A 2008 or VR 8305 P with step opening (special applications).
BURNER DESCRIPTION
The
Two electrodes act as a sparker and a flame rod (See Fig. 1). Flame rectification by this flame rod monitors the continued presence of the burner flame. With three trials for ignition consistency (with Fenwal control), trouble free, safe operation is achieved.
Warning: Should overheating occur, 1) shut off the manual gas shut off valve to control the appliance; 2) DO NOT shut off the control switch to the pump or blower
This power gas burner is designed to convert oil and/or coal fired boilers and furnaces to a
Fig. 1 Electrode and Flame Sensor Dimensions
3
CONVERTING OIL TO GAS
Before attempting the gas conversion, check to insure the heating system is properly sized for the total heating demand and the entire system is in good operating condition, including the fire chamber and flue passages. It is important to allow adequate clearance around the appliance for servicing and proper operation of the burner.
CONVERTING COAL TO GAS
When converting a coal appliance to gas, the coal firing chamber or the ash pit chamber may be used as a gas firing chamber, provided the flame does not impinge on the walls of the appliance (see Chart 2). It is important to allow adequate clearance around the appliance for servicing and proper operation of the burner.
Chart 2: Minimum Firing Chamber Dimensions
AIR FOR COMBUSTION
If the boiler or furnace room is unusually tight, or if the house has a ventilation fan, it is recommended that the combustion air be supplied to the furnace room through intakes from the outside of the building. The intakes must terminate facing down in order to avoid obstruction from rain, snow, leaves, etc. Openings must have one square inch of free area per 10,000 BTU input rate (see Example 1). Follow the heat exchanger manufacturer??s recommendations for installing louvers, etc.
Example 1: 150,000 BTU/hr firing rate
4
CHIMNEY REQUIREMENTS
The chimney should extend at least 3??? above a flat roof or the highest roof ridge (see Fig. 2) and be free in a radius of 30??? of objects such as tree limbs, other buildings, etc, which may cause a down draft. The chimney should be lined as required by the local Gas Company or local codes.
Some utilities require new chimney liners for all gas installations. Use a corrosion resistant chimney liner (approved for gas service) of the same size as the vent pipe.
Fig. 2 Chimney and Fresh Air Dimensions
5
VENT PIPE AND DRAFT HOOD SIZES
Refer to Chart 3 to properly size the flue pipe. If the flue pipe exceeds 10??? in length (including elbows), use the next larger diameter flue pipe and draft hood. If a draft regulator is required, any Canadian Standards Association (CSA) or Underwriter???s Laboratory (UL) listed double swing draft regulator must be used. A movable internal damper is not permitted on gas installations. When the burner is used as a conversion burner, draft over fire should be maintained as
The sizing below does not apply on any factory listed packaged units.
Chart 3: Vent Pipe Sizing
INSTALLING THE BURNER
If the burner being installed is a conversion burner, use a prefabricated chamber or build a firing chamber that can withstand 2000o F (See Chart 2 on page 3). Measure the boiler or furnace mounting plate to determine the flame tube insertion required. Deduct ????? from the total length and tighten the flange on the flame tube with the deducted insertion depth. The ????? deduction will prevent the tip of the flame tube from burning off. Install the burner on the unit and then tighten the nuts on the flange so that the burner is permanently secured. Seal off any free openings with high temperature cement.
Refer to the pictures below to determine which flange is installed on the
Picture 1: STANDARD FLANGE:
Install the gasket and the Standard flange to the boiler. Tighten the bolts. Measure the boiler or furnace- mounting plate to determine the flame tube insertion depth required and make a mark on the tube (with a marker or screwdriver). Deduct ????? from the total length and tighten the flange on the flame tube with the deducted insertion depth. The ????? deduction will prevent the tip of the flame tube from burning off. Slide the blast tube into the boiler to the proper depth and tighten the four
6
Picture 2: DIE CAST FLANGE: (picture to the left) Install the gasket and Die Cast flange to the boiler.
Tighten the bolts. Measure the boiler or
Picture 2: BODY FLANGE: (picture to the left)
First, install the gasket and boiler flange to the boiler.
???For heat exchangers with a diamond stud pattern, one allen screw on the flange should be on the top, slightly to the left of the 12 o???clock stud. The second screw should be on the right (slightly above the 3 o???clock position stud). Tighten all the nuts equally. Make sure that the allen screws are backed out, to allow enough clearance. Then, insert the
???For heat exchangers with a square stud pattern, move one of the allen screws so that both are under the top two boiler studs. Tighten the bolts and install the burner. Make sure the burner is straight and tighten the allen screws.
???Seal off any free openings with either high temperature cement or high temperature silicone.
GAS SERVICE & PIPE CAPACITY
Before connecting the burner to the gas supply, insure that the gas pipes and service meter are large enough to permit the additional load of the gas burner (see Chart 4).
Chart 4: Pipe Capacity Table*( x 1,000 BTU???s)
Nominal diameter of pipe in inches
*Using 0.6 Specific Gravity Gas and a Pressure Drop of 0.3??? of Water Column
**Each 900 elbow counts as 3??? for the purpose of these calculations
7
It is advisable to run a separate gas line from the meter to the gas burner to avoid pressure drops. Refer to the above Pipe Capacity table for the correct sizes. ALL PIPING MUST CONFORM TO LOCAL CODES. Use black steel pipe and malleable fittings (do not use cast iron parts) with a suitable pipe dope that is resistant to liquefied petroleum gases. Test for gas leaks using an approved gas leak tester.
Piping should consist of:
1.A shut off valve approximately 6??? away from the unit.
2.A 1/8??? plugged NPT tapping for gas pressure measurement preferably on the manual shut off valve (as shown or anywhere between the gas valve and the shut off value).
Note: The manual
3.A gas union.
4.A drip pipe.
Caution: The gas valve should not be subjected to more than ????? PSIG. Therefore, the burner should be isolated during
Fig. 3 Gas Burner Piping*
*The dotted lines represent field installation.
To determine the firing rate of the burner, multiply the heating capacity of the appliance by 1.2, or multiply the flow rate in GPH by 140,000 BTU/gal.
Example 2: if the boiler or furnace is rated for 0.75 GPH of No. 2 oil, then: 0.75 GPH x 140,000 = 105,000 BTU input rate.
Use the calculated input rate to fire the boiler or furnace.
8
ORIFICE INSTALLATION
All burners are equipped with an orifice set at the minimum firing rate (except for OEM packaged units). Drilling the orifice increases the firing rate. To drill the orifice, first open the union and then unscrew the orifice from inside the union. Determine the proper orifice size for the desired firing rate and drill the orifice (see Chart 5). Replace the orifice in the union and tighten the union so that it is gas tight. Once installed, a higher or lower firing rate can be achieved by raising or lowering the manifold pressure by +/- 0.3???. Pressure changes can only be made when the burner is running. The typical working manifold pressure for natural gas is 3.5??? W.C. (2.3??? W.C. for LP). The maximum inlet pressure at the gas valve is 11??? W.C.; the minimum is 5??? W.C. (for the purpose of input adjustment).
Note: The manifold pressure may vary for OEM packaged units.
Chart 5: Burner Orifice Sizing For Natural Gas And LP*
* Assumes 0??? to
INSTALLING THE CHIMNEY LINER, DRAFT DIVERTER AND
VENT PIPE
Some utilities require new chimney liners for all gas installations. Use a corrosion resistant chimney liner (approved for gas service) of the same size as the vent pipe. Use an CSA or U.L. listed draft diverter only if you can maintain draft over fire. Otherwise, it is better to use a double swing draft regulator, listed by CSA or U.L. When the burner is used as a conversion burner, draft over fire should be maintained as
9
ELECTRIC WIRING
These gas burners are manufactured for use with 120 volt, 60 cycle,
Installation wiring should be wired through each limit control or interlock, while operating controls (like the thermostat) should be treated as
Fig. 4 Wiring Diagram for Fenwal 2466H
SEQUENCE OF OPERATIONS
Fenwal 2466H
1.All limits are closed and
2.
3.Burner motor starts and
4.Burner housing pressurizes and proves air flow - contacts closed. {Note: if the contacts are closed before the motor starts, blower motor runs continuously. Diagnostic light flashes once every 3 seconds.}
5.At the end of
6.Within 4 seconds, gas flame is established and the flame rod carries current to prove the flame {Note: a minimum of 0.7 micro amps are required; 5 micro amps is not uncommon.}
7.Flame remains till operating limit is open. If
8.If the flame is not established, the control will attempt ignition two more times before locking out for 60 minutes. The control will then attempt to
10
Fig. 5 Wiring Diagram for Honeywell S89F
SEQUENCE OF OPERATIONS
Honeywell S89F
1.Limits close.
2.Blower motor starts as the 24 Volt transformer powers the airflow switch.
3.Power from the airflow switch to the S89F control initiates 34 second
4.At the end of the
5.Within 4 seconds, the flame should be established and proved. The spark will shut off and the control will hold power to the gas valve until the limits open and the burner stops firing.
6.If the flame is not established, the blower motor continuously runs.
7.To restart, power should be interrupted for five minutes. Then turn on the power to start this sequence again.
11
LIGHTING INSTRUCTIONS
BURNER OPERATION
Before turning the burner on, check for gas supply leaks. Check the wiring diagrams; install manometers before and after the gas valve. Keep the observation port of the boiler or furnace open. Follow the instructions on the nameplate of the burner to turn it on. Follow the sequence of operations for the control (see pages 9 and 10). Use a combustion analyzer and record the readings below.
BURNER OPERATION: Record the Readings at Steady State
Draft over fire at steady state (should be
NOTE: This may vary for OEM applications.
Natural Gas CO2 % = (9.0% to 9.8%) or O2 % = (5.0% to 3.5%)
LP Gas CO2 % = (10.5% to 11.5%) or O2 % = (5.0% to 3.5%)
Stack Temperature (300o F minimum, 550oF maximum)
Percentage of Carbon Monoxide (CO) in PPM
Incoming Gas/LP pressure = ???W.C. (minimum 5???)
Natural Gas manifold gas pressure = ???W.C. (3.5??? required + - 0.3???)
NOTE: This may vary for OEM applications.
LP Gas manifold gas pressure = ???W.C. (2.3??? required + - 0.3???)
Carbon Monoxide in flue ( less than 100 PPM ideal; should not exceed 400 PPM Oxygen free)
When to adjust the Air
The air shutter is a mechanical shutter. Do NOT over crank the air shutter. General rule: if the CO2 (Carbon Dioxide) is too low, then close the air shutter. If the CO2 is too high, then open the air shutter. Note: Do NOT set the CO2 higher than 9.8% for Natural Gas or 11.5% for LP Gas.
If the CO (Carbon Monoxide) is above 100 ppm, there is either too much air or too little air. Check the CO2 level and adjust the burner.
When to adjust the Head
The retention head is 1/8??? inside the tube when the marking reads ???22???. There is a full ????? movement for the retention disk to move backward (to increase secondary air) or forwards (to decrease secondary air). NOTE: the head physically moves within the blast tube. Do not over crank the head dial. This movement can also be used to compensate for backpressure in the combustion area, up to 0.3??? W.C.
Caution: If this is the case, the flange and the combustion chamber should be completely
sealed. This pressure firing decreases as the firing rate increases. See Graph 1. Note: the burner should be adjusted while it is firing.
Graph 1: Chamber Pressure versus Firing Rate (BTU)
13
Trouble shooting:
There are three factors to operate the gas burner properly:
1.Electricity {(main Power 120V/60 Hz /1 Ph)( secondary 24V)}
2.Gas flow (Incoming pressure should be 10??? w.c. with proper gas line without pressure drop during burner operation).
3.Combustion air.
Check these three items properly before proceeding in detail for other problems.
7. Condensation in the heat exchanger
Firing Rate is too low.
Increase the firing rate so that the stack temperature is 350o F or HIGHER. Insulate the chimney.
14
15
Maintenance Instructions:
TO BE FIXED/ATTACHED NEAR BURNER
Once a year, a qualified service agency needs to be contracted for other than routine maintenance.
1.The blower motor is the only moving part. It does not require lubrication, since the ball bearings have been permanently lubricated.
2.The user should do periodic visual checks of the burner and the flame.
3.Laundry lint or dog and/or cat hairs should not go inside the blower. If they are seen, they should be removed after disconnecting the power to the burner and cover parts should be installed before starting the burner.
4.Keep the area around the conversion burner clear and free from combustible materials, gasoline, and other flammable vapors and liquids.
5.No obstruction for the flow of combustion and ventilating air (ref. Page 4).
16